Case C-929/26, Asociația Declic – strategic mines and the right to know
The Critical Raw Materials Act was written to get mines and processing plants approved faster. The first reference on it asks whether it also lets governments say less about them.
Facts
Asociația Declic is in proceedings against the Romanian Ministry of Economy, Digitalisation, Entrepreneurship and Tourism before the Curtea de Apel Cluj (Court of Appeal, Cluj). The questions concern public access to information on the process by which a project is recognised as a “strategic project” under Regulation (EU) 2024/1252, the Critical Raw Materials Act. Article 46 of that Regulation, on the handling of confidential information, provides that information acquired in implementing it “shall be used only for the purposes of this Regulation and shall be protected by the relevant Union and national law”. Member States and the Commission must protect “trade and business secrets and other sensitive, confidential and classified information”, and officials must ensure confidentiality “in accordance with relevant Union or national law”. The Court of Appeal asks whether Article 46 creates a general exclusion of public access, whether it is valid if it does, and how it is to be read consistently with the Aarhus Convention.
Questions Referred
1. Must Article 46 of Regulation (EU) 2024/1252 of the European Parliament and of the Council of 11 April 2024 establishing a framework for ensuring a secure and sustainable supply of critical raw materials and amending Regulations (EU) No 168/2013, (EU) 2018/858, (EU) 2018/1724 and (EU) 2019/1020, which relates to the handling of confidential information, be interpreted as meaning that it establishes a general and automatic exclusion from public access to all information relating to the process adopted to recognise a project as a ‘strategic project’ or, on the contrary, that it merely requires compliance with the confidentiality obligations and the protection rules laid down by EU law and by the relevant national law only in respect of information of that nature?
2. Is Article 46 of Regulation (EU) 2024/1252 invalid in so far as it permits the exclusion of public access to environmental information relating to the process adopted to recognise a project as a ‘strategic project’, having regard to the obligations arising from the Aarhus Convention – to which the European Union is a party – and from Regulation (EC) No 1367/2006 on the application of the provisions of the Aarhus Convention to EU institutions and bodies?
3. Is Article 46 of Regulation (EU) 2024/1252, in so far as it is interpreted as establishing rules of absolute confidentiality for environmental information – excluding any public access to such information – compatible with the principle of representative democracy and transparency (Article 1 and Article 10(3) TEU, Article 15 TFEU), with the principle of protection of the environment and the precautionary principle (Article 191 TFEU), with the principle of the rule of law (Article 11 TEU), and with the fundamental rights to good administration, of access to documents and to an effective remedy (Articles 41, 42 and 47 of the Charter of Fundamental Rights of the European Union), as well as with freedom of expression and information (Article 11 of the Charter)?
4. If [the Court of Justice of the European Union] does not rule that Article 46 of Regulation (EU) 2024/1252 is invalid, does the principle of consistent interpretation of secondary EU law require that that article be interpreted as meaning that the confidentiality rules established therein cannot exclude public access to environmental information, public participation in environmental decision-making or the right to an effective remedy, as guaranteed by the Aarhus Convention, Regulation (EC) No 1367/2006 and Articles 11, 41, 42 and 47 of the Charter of Fundamental Rights of the European Union?
Sources
OJ notice C/2026/5972 (EUR‑Lex) · Case file on CURIA · Regulation (EU) 2024/1252 · Directive 2003/4/EC
Comment
The first question may make the others unnecessary. Article 46 does not, on its face, create a new ground for refusing access. It requires information to be “protected by the relevant Union and national law” and confidentiality to be ensured “in accordance with relevant Union or national law”. That wording points to the existing rules on secrecy rather than replacing them. The rules that matter here are those on environmental information. For a national ministry these are in Directive 2003/4/EC, which implements the Aarhus Convention for public authorities in the Member States. Under Article 4(2) of that Directive, the grounds for refusing access “shall be interpreted in a restrictive way”, the public interest in disclosure must be weighed “in every particular case”, and several grounds, including commercial confidentiality, cannot be invoked where the request “relates to information on emissions into the environment”.
Read that way, Article 46 protects genuine trade secrets and classified material within the strategic-project file, but does not close the file. The second and third questions, on validity, arise only if the Court reads Article 46 as a blanket exclusion. If it did, the provision would be hard to reconcile with the Union’s obligations under the Aarhus Convention, to which the Union is a party. The referring court cites Regulation 1367/2006, which applies to Union institutions; the Commission and the Board established by the Act also handle strategic-project applications, so the point is not confined to national authorities.
The fourth question points to the most likely outcome: an interpretation in conformity with the Convention and the Charter. In practice, it would decide how much an applicant for a strategic project can expect to keep from the public. The Act’s purpose is speed. Strategic projects benefit from accelerated permitting, and public participation depends on knowing what is proposed. A ruling that the confidentiality clause adds nothing to the ordinary rules would preserve that knowledge without touching the timetable.